Weekly Report

Weekly Progress Report # 40





Item Description  Previous
Week
 This week  Next to  week
1 INITIAL WORKS
Mobilization 100.00% 100.00%
Setting Out 100.00% 100.00%
Site clearing, grading area for temporary facilities 100.00% 100.00%
Temporary access road and drainage 100.00% 100.00%
100.00% 100.00%
2 CONSTRUCTION FACILITIES AND TEMPORARY WORKS 100.00% 100.00%
Temporary site office for Pisnoka (1 container 24 feet, rental fee) 100.00% 100.00%
Temporary storage (2 container 24 feet, rental fee) 100.00% 100.00%
Labor camps/domitory (Land area provided by clients, camp) 100.00% 100.00%
Accomdation for managers and supervisors (home rental) 100.00% 100.00%
Temporary guard house (1 labor camp, 1 at job site) 100.00% 100.00%
Temporary toilet for labors (3mx5m) 100.00% 100.00%
Temporary toilet for staff 100.00% 100.00%
Temporary workshop for rebar(12mx10m) 100.00% 100.00%
Temporary workshop for formwork(12mx10m) 100.00% 100.00%
Temporary parking area 100.00% 100.00%
Grand House
I. STRUCTURAL WORKS-follow new update structural drawing 100.00% 100.00%
A. Piling Works 100.00% 100.00%
1 PC Pile 300x300mm , Bottom pile L= 23.0m depth 100.00% 100.00%
2 Pile top cut-off for PC Pile 300mmx300mm as required level 100.00% 100.00%
B. Earthwork-follow new update structural drawing 100.00% 100.00%
1 Soil excavation for slab, lift pit, pile cap, underground beam, water tank 100.00% 100.00%
2 Sandy backfilling and compaction 100.00% 100.00%
3 soil Disposal 100.00% 100.00%
4 Lean concrete,50mm thk (pile cap, ground beam and ground floor slab, water tank) 100.00% 100.00%
5 Compacted coarse sand/crushed stone M30, thk100mm 100.00% 100.00%
6 Plastic sheet 100.00% 100.00%
7 Anti-Termite Granules (slab) 100.00% 100.00%
C. Substructure Concrete Works- follow new update structural drawing 100.00% 100.00%
1 Concrete: fcyl=28MPa 100.00% 100.00%
RC pile cap 100.00% 100.00%
RC stump column 100.00% 100.00%
RC wall lift pit 100.00% 100.00%
Water tank (10.70x10.60m - H=1.450) 100.00% 100.00%
D. Supertructure Concrete Works 100.00% 100.00%
Floor Level 1 (Ground ) 100.00% 100.00%
1 Concrete: fcyl=28MPa 100.00% 100.00%
RC Beam 100.00% 100.00%
RC slab 100.00% 100.00%
RC column 100.00% 100.00%
RC wall 100.00% 100.00%
RC at loading are (Ramp) 100.00% 100.00%
RC Parapet Wall thk=100mm for molding 100.00% 100.00%
RC Internal Staircase 100.00% 100.00%
RC External Staircase including brick wall support 100.00% 100.00%
brick 10cm support concrete 100.00% 100.00%
brick 20cm support concrete 100.00% 100.00%
4 Post Tension Cable 100.00% 100.00%
Floor Level 2 100.00% 100.00%
RC Beam 100.00% 100.00%
RC slab 100.00% 100.00%
RC column 100.00% 100.00%
RC wall 100.00% 100.00%
RC Parapet Wall thk=100mm for molding 100.00% 100.00%
RC Staircase 100.00% 100.00%
RC Gutter 100.00% 100.00%
4 Post Tension Cable 100.00% 100.00%
Floor Level 3 100.00% 100.00%
RC Beam 100.00% 100.00%
RC slab 100.00% 100.00%
RC column 100.00% 100.00%
RC wall 100.00% 100.00%
RC Parapet Wall thk=100mm for molding 100.00% 100.00%
RC Gutter 100.00% 100.00%
4 Post Tension Cable 100.00% 100.00%
Roof Floor Level 3 100.00% 100.00%
RC Beam 100.00% 100.00%
RC Parapet Wall thk=100mm for molding 100.00% 100.00%
RC Gutter 100.00% 100.00%
E. Structural Steel Works 100.00% 100.00%
Roof level 1 100.00% 100.00%
1 Roof tile 100.00% 100.00%
2 Purlin 100.00% 100.00%
Roof level 2 100.00% 100.00%
1 Roof tile 100.00% 100.00%
2 Purlin 100.00% 100.00%
Roof level 3 100.00% 100.00%
1 Roof tile 100.00% 100.00%
2 Purlin 100.00% 100.00%
II. ARCHITECTURAL WORKS
A Masonry works
Floor Level 1 (Ground )
1 Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid 20.00% 10.00% 30.00%
2 Double layers of brick wall 75mm thk. 20.00% 10.00% 30.00%
3 Double layers of brick wall 75mm thk. with air space 20cm. 20.00% 10.00% 30.00%
4 Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner 20.00% 10.00% 30.00%
horizontal lintel 100x120mm for single brick 75mm 20.00% 10.00% 30.00%
Vertical lintel 100x400mm for double brick 75mm with air space 200mm 20.00% 10.00% 30.00%
Floor Level 2 0.00%
1 Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid 0.00% 0.00% 0.00%
2 Double layers of brick wall 75mm thk. 0.00% 0.00% 0.00%
3 Double layers of brick wall 75mm thk. with air space 20cm. 0.00% 0.00% 0.00%
4 Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner 0.00% 0.00% 0.00%
horizontal lintel 100x120mm for single brick 75mm 0.00% 0.00% 0.00%
Floor Level 3
1 Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid 0.00% 0.00% 0.00%
2 Double layers of brick wall 75mm thk. 0.00% 0.00% 0.00%
3 Double layers of brick wall 75mm thk. with air space 20cm. 0.00% 0.00% 0.00%
4 Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner 0.00% 0.00% 0.00%
horizontal lintel 100x120mm for single brick 75mm 0.00% 0.00% 0.00%
B Plastering works
Floor Level 1 (Ground ) 0.00% 0.00% 0.00%
1 Internal plastering 15mm thk. for wall, opening area, column 0.00% 0.00% 0.00%
2 External plastering 15mm thk. for brick wall, column 0.00% 0.00% 0.00%
Floor Level 2 0.00% 0.00% 0.00%
1 Internal plastering 15mm thk. for wall, opening area, column 0.00% 0.00% 0.00%
2 External plastering 15mm thk. for brick wall, column 0.00% 0.00% 0.00%
Floor Level 3 0.00% 0.00% 0.00%
1 Internal plastering 15mm thk. for wall, opening area, column 0.00% 0.00% 0.00%
2 External plastering 15mm thk. for brick wall, column 0.00% 0.00% 0.00%
C Floor/wall tile works/Skirting
Floor 1
F8,F12,F13,-Ceramic floor tile 600x600 0.00% 0.00% 0.00%
F6,F7-Ceramic floor tile 300x300 0.00% 0.00% 0.00%
3, 5- Ceramic wall tile 300X300;300X600 0.00% 0.00% 0.00%
Ceramic tile for stair 0.00% 0.00% 0.00%
Solid wood for stair 0.00% 0.00% 0.00%
F1,F4,F14-Granite floor 20mm 0.00% 0.00% 0.00%
F4, -Granite wall, thk20mm 0.00% 0.00% 0.00%
F2-Marble floor, thk20mm 0.00% 0.00% 0.00%
F3-Wooden floor 0.00% 0.00% 0.00%
Skirting-ceramic tile, h100mm 0.00% 0.00% 0.00%
F15,F16-Polished cement for floor-( cement mortar screed) 0.00% 0.00% 0.00%
7-Polished cement for wall-( cement mortar screed) 0.00% 0.00% 0.00%
7-Polished cement for stair-( cement mortar screed) 0.00% 0.00% 0.00%
Floor 2
F8,F9,-Ceramic floor tile 600x600 0.00% 0.00% 0.00%
F6-Ceramic floor tile 300x300 0.00% 0.00% 0.00%
3,- Ceramic wall tile 300X300;300X600 0.00% 0.00% 0.00%
Ceramic tile for stair 0.00% 0.00% 0.00%
Solid wood for stair 0.00% 0.00% 0.00%
F1,F4,F14-Granite floor 20mm 0.00% 0.00% 0.00%
F4, -Granite wall, thk20mm 0.00% 0.00% 0.00%
F2-Marble floor, thk20mm 0.00% 0.00% 0.00%
F3-Wooden floor 0.00% 0.00% 0.00%
Skirting-ceramic tile, h100mm 0.00% 0.00% 0.00%
F16-Polished cement for floor-( cement mortar screed) 0.00% 0.00% 0.00%
7-Polished cement for wall-( cement mortar screed) 0.00% 0.00% 0.00%
7-Polished cement for stair-( cement mortar screed) 0.00% 0.00% 0.00%
Floor 3
F8,F9,-Ceramic floor tile 600x600 0.00% 0.00% 0.00%
F6,F7-Ceramic floor tile 300x300 0.00% 0.00% 0.00%
3,5- Ceramic wall tile 300X300;300X600 0.00% 0.00% 0.00%
Ceramic tile for stair 0.00% 0.00% 0.00%
Solid wood for stair 0.00% 0.00% 0.00%
F1,F4,F14-Granite floor 20mm 0.00% 0.00% 0.00%
F4, -Granite wall, thk20mm 0.00% 0.00% 0.00%
F2-Marble floor, thk20mm 0.00% 0.00% 0.00%
F3-Wooden floor 0.00% 0.00% 0.00%
Skirting-ceramic tile, h100mm 0.00% 0.00% 0.00%
F16-Polished cement for floor 0.00% 0.00% 0.00%
7-Polished cement for wall 0.00% 0.00% 0.00%
7-Polished cement for stair 0.00% 0.00% 0.00%
Roof Floor
F16-Polished cement for floor-( cement mortar screed) 0.00% 0.00% 0.00%
F7-Polished cement for wall-( cement mortar screed) 0.00% 0.00% 0.00%
F7-Polished cement for stair-( cement mortar screed) 0.00% 0.00% 0.00%
E Waterproofing works
Floor1
Cementious waterproofing work at WC/bathroom area 0.00% 0.00% 0.00%
Cementious waterproofing work for water tank 0.00% 0.00% 0.00%
Cementious waterproofing work at terrace, kitchen, pumproom,laundry  0.00% 0.00% 0.00%

Daily Report

Project: LYP’s Residence  
Contractor: PISNOKA International Corporation 
Date:  23-July-2019
 
No: LYP-280
Average number of workers 


            Management               :   1
            Supervisor/ Engineers   :   3
            HSE                               :   2
            MEP Staff                      :   2
            Archicture                       :  1
            Office Staff                     :   2
            Un-skilled                       :   150
            Sub Contractor               :   30
                                                                       Equipment                                                                      

- Wheel Loader (1)                                                

- 25 Ton Crane (1)

- 55 Ton Crane (1)

- Roller (1)

- Bulldozer (1)

- Dumping truck (1)

- Excavator

- Tower Crane 
                                                                 Machinery on site:

-Cutting machine gas (2)

-Grinding machine (3)

-Cutting motor (9)

-Generator GT 60 kva (1)

-Generator GT 30 kva (2)

-Generator GT 150 kva (1)

-Generator GT 250 kva (1)
-Flat compactor (4)
                                                                 Works Carried Out:

1)    Temporary site facility

  • Temporary Work Camp                                           
  • Temporary House keeping

2)    Security House I&II

·         Bricklaying for Molding

·         Plastering for Molding

·         Steel Structure Work

3)    Car Parking, I&II

·         Brick Laying

·         Plastering Work

·         Apply Waterproofing of Gutter

·         Steel Structure Work

4)    Dinning Pool
Steel Structure Work for roof tile
5)    Grand House

·         Bricklaying

·         Remove Formwork of Second Floor Beam

·         Install Rebar and Formwork of Lintel

·         Installation Scaffolding for Supporting First Floor Beam

·         Cleaning Surface Concrete gutter

·         Apply Waterproofing (Brush Bound)

·         Mortar Topping with Slope of Roof Gutter

·         Casting Concrete of First Floor Beam

6)    Fitness
Installation Rebar of Column  
Photo Attachment