Monthly Progress Report for JUNE 2019 | ||||
Item | Description | Previous month MAY 2019 |
This Month JUNE 2019 |
Next to Month JULY 2019 |
1 | INITIAL WORKS | |||
Mobilization | 100.00% | 100.00% | ||
Setting Out | 100.00% | 100.00% | ||
Site clearing, grading area for temporary facilities | 100.00% | 100.00% | ||
Temporary access road and drainage | 100.00% | 100.00% | ||
100.00% | 100.00% | |||
2 | CONSTRUCTION FACILITIES AND TEMPORARY WORKS | 100.00% | 100.00% | |
Temporary site office for Pisnoka (1 container 24 feet, rental fee) | 100.00% | 100.00% | ||
Temporary storage (2 container 24 feet, rental fee) | 100.00% | 100.00% | ||
Labor camps/domitory (Land area provided by clients, camp) | 100.00% | 100.00% | ||
Accomdation for managers and supervisors (home rental) | 100.00% | 100.00% | ||
Temporary guard house (1 labor camp, 1 at job site) | 100.00% | 100.00% | ||
Temporary toilet for labors (3mx5m) | 100.00% | 100.00% | ||
Temporary toilet for staff | 100.00% | 100.00% | ||
Temporary workshop for rebar(12mx10m) | 100.00% | 100.00% | ||
Temporary workshop for formwork(12mx10m) | 100.00% | 100.00% | ||
Temporary parking area | 100.00% | 100.00% | ||
Grand House | ||||
I. | STRUCTURAL WORKS-follow new update structural drawing | 100.00% | 100.00% | |
A. | Piling Works | 100.00% | 100.00% | |
1 | PC Pile 300x300mm , Bottom pile L= 23.0m depth | 100.00% | 100.00% | |
2 | Pile top cut-off for PC Pile 300mmx300mm as required level | 100.00% | 100.00% | |
B. | Earthwork-follow new update structural drawing | 100.00% | 100.00% | |
1 | Soil excavation for slab, lift pit, pile cap, underground beam, water tank | 100.00% | 100.00% | |
2 | Sandy backfilling and compaction | 100.00% | 100.00% | |
3 | soil Disposal | 100.00% | 100.00% | |
4 | Lean concrete,50mm thk (pile cap, ground beam and ground floor slab, water tank) | 100.00% | 100.00% | |
5 | Compacted coarse sand/crushed stone M30, thk100mm | 100.00% | 100.00% | |
6 | Plastic sheet | 100.00% | 100.00% | |
7 | Anti-Termite Granules (slab) | 100.00% | 100.00% | |
C. | Substructure Concrete Works- follow new update structural drawing | 100.00% | 100.00% | |
1 | Concrete: fcyl=28MPa | 100.00% | 100.00% | |
RC pile cap | 100.00% | 100.00% | ||
RC stump column | 100.00% | 100.00% | ||
RC wall lift pit | 100.00% | 100.00% | ||
Water tank (10.70x10.60m - H=1.450) | 100.00% | 100.00% | ||
D. | Supertructure Concrete Works | 100.00% | 100.00% | |
Floor Level 1 (Ground ) | 100.00% | 100.00% | ||
1 | Concrete: fcyl=28MPa | 100.00% | 100.00% | |
RC Beam | 100.00% | 100.00% | ||
RC slab | 100.00% | 100.00% | ||
RC column | 100.00% | 100.00% | ||
RC wall | 100.00% | 100.00% | ||
RC at loading are (Ramp) | 100.00% | 100.00% | ||
RC Parapet Wall thk=100mm for molding | 100.00% | 100.00% | ||
RC Internal Staircase | 100.00% | 100.00% | ||
RC External Staircase including brick wall support | 100.00% | 100.00% | ||
brick 10cm support concrete | 100.00% | 100.00% | ||
brick 20cm support concrete | 100.00% | 100.00% | ||
4 | Post Tension Cable | 100.00% | 100.00% | |
Floor Level 2 | 100.00% | 100.00% | ||
RC Beam | 100.00% | 100.00% | ||
RC slab | 100.00% | 100.00% | ||
RC column | 100.00% | 100.00% | ||
RC wall | 100.00% | 100.00% | ||
RC Parapet Wall thk=100mm for molding | 100.00% | 100.00% | ||
RC Staircase | 100.00% | 100.00% | ||
RC Gutter | 100.00% | 100.00% | ||
4 | Post Tension Cable | 100.00% | 100.00% | |
Floor Level 3 | 100.00% | 100.00% | ||
RC Beam | 100.00% | 100.00% | ||
RC slab | 100.00% | 100.00% | ||
RC column | 100.00% | 100.00% | ||
RC wall | 100.00% | 100.00% | ||
RC Parapet Wall thk=100mm for molding | 100.00% | 100.00% | ||
RC Gutter | 100.00% | 100.00% | ||
4 | Post Tension Cable | 100.00% | 100.00% | |
Roof Floor Level 3 | 100.00% | 100.00% | ||
RC Beam | 100.00% | 100.00% | ||
RC Parapet Wall thk=100mm for molding | 100.00% | 100.00% | ||
RC Gutter | 100.00% | 100.00% | ||
E. | Structural Steel Works | 100.00% | 100.00% | |
Roof level 1 | 100.00% | 100.00% | ||
1 | Roof tile | 100.00% | 100.00% | |
2 | Purlin | 100.00% | 100.00% | |
Roof level 2 | 100.00% | 100.00% | ||
1 | Roof tile | 100.00% | 100.00% | |
2 | Purlin | 100.00% | 100.00% | |
Roof level 3 | 100.00% | 100.00% | ||
1 | Roof tile | 100.00% | 100.00% | |
2 | Purlin | 100.00% | 100.00% | |
II. | ARCHITECTURAL WORKS | |||
A | Masonry works | |||
Floor Level 1 (Ground ) | ||||
1 | Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid | 10.00% | 10.00% | 20.00% |
2 | Double layers of brick wall 75mm thk. | 10.00% | 10.00% | 20.00% |
3 | Double layers of brick wall 75mm thk. with air space 20cm. | 10.00% | 10.00% | 20.00% |
4 | Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner | 10.00% | 10.00% | 20.00% |
horizontal lintel 100x120mm for single brick 75mm | 10.00% | 10.00% | 20.00% | |
Vertical lintel 100x400mm for double brick 75mm with air space 200mm | 10.00% | 10.00% | 20.00% | |
Floor Level 2 | ||||
1 | Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid | 0.00% | 0.00% | 0.00% |
2 | Double layers of brick wall 75mm thk. | 0.00% | 0.00% | 0.00% |
3 | Double layers of brick wall 75mm thk. with air space 20cm. | 0.00% | 0.00% | 0.00% |
4 | Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner | 0.00% | 0.00% | 0.00% |
horizontal lintel 100x120mm for single brick 75mm | 0.00% | 0.00% | 0.00% | |
Floor Level 3 | 0.00% | 0.00% | 0.00% | |
1 | Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid | 0.00% | 0.00% | 0.00% |
2 | Double layers of brick wall 75mm thk. | 0.00% | 0.00% | 0.00% |
3 | Double layers of brick wall 75mm thk. with air space 20cm. | 0.00% | 0.00% | 0.00% |
4 | Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner | 0.00% | 0.00% | 0.00% |
horizontal lintel 100x120mm for single brick 75mm | 0.00% | 0.00% | 0.00% | |
B | Plastering works | |||
Floor Level 1 (Ground ) | 0.00% | 0.00% | 0.00% | |
1 | Internal plastering 15mm thk. for wall, opening area, column | 0.00% | 0.00% | 0.00% |
2 | External plastering 15mm thk. for brick wall, column | 0.00% | 0.00% | 0.00% |
Floor Level 2 | 0.00% | 0.00% | 0.00% | |
1 | Internal plastering 15mm thk. for wall, opening area, column | 0.00% | 0.00% | 0.00% |
2 | External plastering 15mm thk. for brick wall, column | 0.00% | 0.00% | 0.00% |
Floor Level 3 | 0.00% | 0.00% | 0.00% | |
1 | Internal plastering 15mm thk. for wall, opening area, column | 0.00% | 0.00% | 0.00% |
2 | External plastering 15mm thk. for brick wall, column | 0.00% | 0.00% | 0.00% |
C | Floor/wall tile works/Skirting | |||
Labor cost only : cement mortar is included; excluded tile material & tile joint grouting , tile adhesive-glue | ||||
Floor 1 | ||||
F8,F12,F13,-Ceramic floor tile 600x600 | 0.00% | 0.00% | 0.00% | |
F6,F7-Ceramic floor tile 300x300 | 0.00% | 0.00% | 0.00% | |
3, 5- Ceramic wall tile 300X300;300X600 | 0.00% | 0.00% | 0.00% | |
Ceramic tile for stair | 0.00% | 0.00% | 0.00% | |
Solid wood for stair | 0.00% | 0.00% | 0.00% | |
F1,F4,F14-Granite floor 20mm | 0.00% | 0.00% | 0.00% | |
F4, -Granite wall, thk20mm | 0.00% | 0.00% | 0.00% | |
F2-Marble floor, thk20mm | 0.00% | 0.00% | 0.00% | |
F3-Wooden floor | 0.00% | 0.00% | 0.00% | |
Skirting-ceramic tile, h100mm | 0.00% | 0.00% | 0.00% | |
F15,F16-Polished cement for floor-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
7-Polished cement for wall-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
7-Polished cement for stair-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
Floor 2 | ||||
F8,F9,-Ceramic floor tile 600x600 | 0.00% | 0.00% | 0.00% | |
F6-Ceramic floor tile 300x300 | 0.00% | 0.00% | 0.00% | |
3,- Ceramic wall tile 300X300;300X600 | 0.00% | 0.00% | 0.00% | |
Ceramic tile for stair | 0.00% | 0.00% | 0.00% | |
Solid wood for stair | 0.00% | 0.00% | 0.00% | |
F1,F4,F14-Granite floor 20mm | 0.00% | 0.00% | 0.00% | |
F4, -Granite wall, thk20mm | 0.00% | 0.00% | 0.00% | |
F2-Marble floor, thk20mm | 0.00% | 0.00% | 0.00% | |
F3-Wooden floor | 0.00% | 0.00% | 0.00% | |
Skirting-ceramic tile, h100mm | 0.00% | 0.00% | 0.00% | |
F16-Polished cement for floor-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
7-Polished cement for wall-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
7-Polished cement for stair-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
Floor 3 | ||||
F8,F9,-Ceramic floor tile 600x600 | 0.00% | 0.00% | 0.00% | |
F6,F7-Ceramic floor tile 300x300 | 0.00% | 0.00% | 0.00% | |
3,5- Ceramic wall tile 300X300;300X600 | 0.00% | 0.00% | 0.00% | |
Ceramic tile for stair | 0.00% | 0.00% | 0.00% | |
Solid wood for stair | 0.00% | 0.00% | 0.00% | |
F1,F4,F14-Granite floor 20mm | 0.00% | 0.00% | 0.00% | |
F4, -Granite wall, thk20mm | 0.00% | 0.00% | 0.00% | |
F2-Marble floor, thk20mm | 0.00% | 0.00% | 0.00% | |
F3-Wooden floor | 0.00% | 0.00% | 0.00% | |
Skirting-ceramic tile, h100mm | 0.00% | 0.00% | 0.00% | |
F16-Polished cement for floor | 0.00% | 0.00% | 0.00% | |
7-Polished cement for wall | 0.00% | 0.00% | 0.00% | |
7-Polished cement for stair | 0.00% | 0.00% | 0.00% | |
Roof Floor | ||||
F16-Polished cement for floor-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
F7-Polished cement for wall-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
F7-Polished cement for stair-( cement mortar screed) | 0.00% | 0.00% | 0.00% | |
E | Waterproofing works | |||
Floor1 | ||||
Cementious waterproofing work at WC/bathroom area | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work for water tank | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at terrace, kitchen, pumproom,laundry | 0.00% | 0.00% | 0.00% | |
Floor2 | ||||
Cementious waterproofing work at WC/bathroom area | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work for water tank | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at Laundry store, pantry room | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at service terrace, belcony | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at gutter | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at molding gutter | 0.00% | 0.00% | 0.00% | |
Asphalt waterproofing work roof slab | 0.00% | 0.00% | 0.00% | |
Floor3 | ||||
Cementious waterproofing work at WC/bathroom area | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work for water tank | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at Laundry store, pantry room | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at deck, belcony | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work inside gutter | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at molding gutter | 0.00% | 0.00% | 0.00% | |
Asphalt waterproofing work roof slab | 0.00% | 0.00% | 0.00% | |
Roof floor | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work inside gutter | 0.00% | 0.00% | 0.00% | |
Cementious waterproofing work at molding gutter | 0.00% | 0.00% | 0.00% | |
F | RC curb at toilet area | |||
Floor Level 1 (Ground ) | ||||
RC curb 100x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
RC curb 200x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
RC curb 400x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
Floor Level 2 | ||||
RC curb 100x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
RC curb 200x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
RC curb 400x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
Floor Level 3 | ||||
RC curb 100x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
RC curb 400x200mm for support toilet wall | 0.00% | 0.00% | 0.00% | |
G | Molding for column | |||
Floor Level 1 (Ground ) | ||||
G.R.C Molding type C1_double columns size : 3.40x1.85m - h=10.05m & additional RC column 0.40x0.40m-h=10.05m | 0.00% | 0.00% | 0.00% | |
Floor Level 2 | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type C1A_double columns size : 3.40x1.85m - h=9.20m & additional RC column 0.40x0.40m-h=10.05m | 0.00% | 0.00% | 0.00% | |
Floor Level 3 | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type C3_single columns size : 0.90x0.90m - h=3.90m | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type C5B_on wall size : 0.65x0.225m - h=3.90m | 0.00% | 0.00% | 0.00% | |
H | Molding for wall, door, window | |||
Floor Level 1 (Ground ) | ||||
G.R.C Molding type B3_0.15x0.08m | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type B4_0.20x0.175m | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type B14_1.05x0.10m | 0.00% | 0.00% | 0.00% | |
Floor Level 2 | ||||
G.R.C Molding type B2_0.60x0.2m | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type B2A_0.85x0.35m | 0.00% | 0.00% | 0.00% | |
Floor Level 3 | ||||
G.R.C Molding type B1_0.60x1.40m | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type B2_0.60x0.2m | 0.00% | 0.00% | 0.00% | |
Roof | 0.00% | 0.00% | 0.00% | |
G.R.C Molding type B1_0.60x1.40m | ||||
G.R.C Molding type B2_0.60x0.2m | 0.00% | 0.00% | 0.00% | |
I | Roof tile_ SCG-CPAC_ Ceramic Roof Excella Collection: serie modern | |||
roof tile level 1 | ||||
Roof tile | 0.00% | 0.00% | 0.00% | |
Roof Eave | 0.00% | 0.00% | 0.00% | |
Roof hip | 0.00% | 0.00% | 0.00% | |
Roof ridge | 0.00% | 0.00% | 0.00% | |
Roof vallege | 0.00% | 0.00% | 0.00% | |
Flashing | 0.00% | 0.00% | 0.00% | |
Purlin | 0.00% | 0.00% | 0.00% | |
Accessories | 0.00% | 0.00% | 0.00% | |
roof tile level 2 | ||||
Roof tile | 0.00% | 0.00% | 0.00% | |
Roof Eave | 0.00% | 0.00% | 0.00% | |
Roof hip | 0.00% | 0.00% | 0.00% | |
Roof ridge | 0.00% | 0.00% | 0.00% | |
Roof vallege | 0.00% | 0.00% | 0.00% | |
Roof rake | 0.00% | 0.00% | 0.00% | |
Flashing | 0.00% | 0.00% | 0.00% | |
Purlin | 0.00% | 0.00% | 0.00% | |
Accessories | 0.00% | 0.00% | 0.00% | |
roof tile level 3 | ||||
Roof tile | 0.00% | 0.00% | 0.00% | |
Roof Eave | 0.00% | 0.00% | 0.00% | |
Roof hip | 0.00% | 0.00% | 0.00% | |
Roof ridge | 0.00% | 0.00% | 0.00% | |
Roof vallege | 0.00% | 0.00% | 0.00% | |
Purlin | 0.00% | 0.00% | 0.00% | |
Accessories | 0.00% | 0.00% | 0.00% | |
Dining Pool | ||||
I. | STRUCTURAL WORKS | |||
A. | Piling Works | |||
1 | PC Pile 300x300mm , Bottom pile L= 23.0m depth | 100.00% | 100.00% | 100.00% |
2 | Pile top cut-off for PC Pile 300mmx300mm as required level | 100.00% | 100.00% | 100.00% |
B. | Earthwork | 100.00% | 100.00% | 100.00% |
1 | Soil excavation for beam, pile cap | 100.00% | 100.00% | 100.00% |
2 | Sandy backfilling and compaction | 100.00% | 100.00% | 100.00% |
3 | soil Disposal | 100.00% | 100.00% | 100.00% |
4 | Lean concrete,50mm thk (pile cap, ground beam and ground floor slab, water tank) | 100.00% | 100.00% | 100.00% |
5 | Plastic sheet | 100.00% | 100.00% | 100.00% |
6 | Anti-Termite Granules (slab) | 100.00% | 100.00% | 100.00% |
C. | Substructure Concrete Works | 100.00% | 100.00% | 100.00% |
1 | Concrete: fcyl=28MPa | 100.00% | 100.00% | 100.00% |
RC pile cap | 100.00% | 100.00% | 100.00% | |
RC stump column | 100.00% | 100.00% | 100.00% | |
2 | Formwork | 100.00% | 100.00% | 100.00% |
RC pile cap | 100.00% | 100.00% | 100.00% | |
RC stump column | 100.00% | 100.00% | 100.00% | |
3 | Reinforcement bar for | 100.00% | 100.00% | 100.00% |
Reinforcement bar for pile cap | 100.00% | 100.00% | 100.00% | |
Reinforcement bar stump column | 100.00% | 100.00% | 100.00% | |
Tie wire | 100.00% | 100.00% | 100.00% | |
D. | Supertructure Concrete Works | 100.00% | 100.00% | 100.00% |
Floor Level 1 (Ground ) | 100.00% | 100.00% | 100.00% | |
1 | Concrete: fcyl=28MPa | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC column | 100.00% | 100.00% | 100.00% | |
RC staircase | 100.00% | 100.00% | 100.00% | |
2 | Formwork | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC column | 100.00% | 100.00% | 100.00% | |
RC staircase | 100.00% | 100.00% | 100.00% | |
3 | Reinforcement bar for | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC column | 100.00% | 100.00% | 100.00% | |
RC staircase | 100.00% | 100.00% | 100.00% | |
Tie wire | 100.00% | 100.00% | 100.00% | |
Roof Floor Level | 100.00% | 100.00% | 100.00% | |
1 | Concrete: fcyl=28MPa | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC Gutter | 100.00% | 100.00% | 100.00% | |
2 | Formwork | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC Gutter | 100.00% | 100.00% | 100.00% | |
3 | Reinforcement bar for | 100.00% | 100.00% | 100.00% |
RC Beam | 100.00% | 100.00% | 100.00% | |
RC slab | 100.00% | 100.00% | 100.00% | |
RC Gutter | 100.00% | 100.00% | 100.00% | |
Tie wire | 100.00% | 100.00% | 100.00% | |
E. | Structural Steel Works | |||
Roof tile | 0.00% | 0.00% | 0.00% | |
Purlin | 70.00% | 70.00% | 70.00% | |
II. | ARCHITECTURAL WORKS | |||
A. | Masonry works | |||
Floor Level 1 (Ground ) | 100.00% | 100.00% | 100.00% | |
Single layer of Brick Wall 75mm thick masonry hollow brick wall with solid brick cross laid | 100.00% | 100.00% | 100.00% | |
Double layers of brick wall 75mm thk. | 100.00% | 100.00% | 100.00% | |
Double layers of brick wall 75mm thk. with air space 20cm. | 100.00% | 100.00% | 100.00% | |
Lintel/stud column for brick wall length > 4m, height >4m, wall end, & wall corner | 100.00% | 100.00% | 100.00% | |
B. | Plastering works | 100.00% | 100.00% | 100.00% |
Floor Level 1 (Ground ) | 100.00% | 100.00% | 100.00% | |
Internal plastering 15mm thk. for wall, opening area, column | 100.00% | 100.00% | 100.00% | |
External plastering 15mm thk. for brick wall, column | 100.00% | 100.00% | 100.00% |
Showing posts with label Monthly Report. Show all posts
Showing posts with label Monthly Report. Show all posts
Saturday, August 10, 2019
Monthly Report
CLICK HERE FOR DOWNLOAD FILE MONTHLY PROGRESS REPORT